Infrastructure Alternatives Integrated solution
Dredging
Sediment Dewatering Technologies
Shoreline Protection
Water and Wastewater Management
Infrastructure Alternatives
Ashtabula River Remediation

     

Project location

 

Summary

  • Ashtabula River, Ashtabula, Ohio

 

Accumulated soft sediment of the lower Ashtabula River in Ashtabula, Ohio, was contaminated with organic chemicals such as polychlorinated biphenyls (PCBs) and polycyclic aromatic hydrocarbons (PAHs), heavy metals and some low level radionuclides.  The Ashtabula River Remediation, a two phase project which began in 2006 and was completed in 2008, utilized hydraulic dredging in conjunction with geotextile tube dewatering to remove, dewater and dispose of the unwanted sediment.  Geotextile tube dewatering technology was very successfully applied in this project, providing an innovative, cost-effective dewatering and disposal option for heavily contaminated soft sediment. 

The scale of the Ashtabula River Remediation, the largest Great Lakes Legacy Act funded project to date, was enormous.  Over the course of the project, performed in two phases over three dredging seasons, about 640,000 cubic yards of contaminated sediment were removed from the river.  Infrastructure Alternatives was contracted by the general contractors of both Phase I & II of the project to design, operate and maintain the sediment dewatering system and was additionally responsible for operation of chemical addition and water treatment processes during Phase II of the project.

Contaminated sediment was removed from the river utilizing a 12 inch diameter hydraulic cutter head dredge.  (The dredging contractor was J.F. Brennan Company of LaCrosse, Wisconsin.)  The sediment transfer pipeline delivered the sediment slurry from the dredge to the sediment Consolidation Facility (CF), where it was dewatered in geotextile tubes.  The CF was a 12.5 acre landfill, permitted under the Toxic Substances Control Act (TSCA), and constructed specifically for the Ashtabula River Remediation project.  The CF was designed not only to provide a dewatering site, but also a permanent disposal site for the dewatered sediment.  At the conclusion of the project, the CF was prepared for capping and closure.

Geotextile tubes were used to dewater the dredged sediment slurry.  As the slurry arrived at the CF, flowing at a rate of up to 5,000 gallons per minute, it was directed through a header system to geotextile tubes which were filled in place inside the CF.  By project’s end, geotextile tubes had been filled and stacked in ten layers, forming a pyramid shape inside the CF.  Weep water (clear water released from the geotextile tubes) drained by gravity to a sump in the CF floor and was processed in an on-site water treatment plant before being discharged back into the Ashtabula River. 

Due to the contamination present in the dredged sediment, Infrastructure Alternatives’ entire project staff of approximately 50 personnel were OSHA 40-hour Hazardous Waste Operations and Emergency Response (HAZWOPER) certified and also received Radiation Worker II training on site.

Services provided

 

  • Geotextile tube dewatering system operation
  • Stacking geotextile tubes to 10 layers
  • Design and construction of geotextile tube header system
  • Chemical conditioning of dredged sediment
  • Operation and maintenance of wastewater treatment system
  • HAZWOPER certified crew
  • Site specific health and safety program

 

Contact us about this project

 

 
   
   
   
   
   
   
   
   
   
   
   
   
   
   

Project Photo Gallery


 

(Photo 1 of 8) Dredged sediment was pumped to a specially constructed containment facility for dewatering in geotextile tubes.  This photo shows the first tubes being filled in the fall of 2006.

 

First geotextile tubes installed in the sediment containment facility, fall 2006

 

 

 

(Photo 2 of 8) Geotextile tubes stacked in the sediment containment facility, summer 2007

 

Geotextile tubes in the sediment containment facility, summer 2007

 

 

 

(Photo 3 of 8) Geotextile tubes stacked to 10 layers in the sediment containment facility, summer 2008

 

Geotextile tubes stacked to 10 layers in the sediment containment facility, summer 2008

 

 

 

(Photo 4 of 8) A portion of the chemical feed system that was used to flocculate the dredged sediment prior to dewatering in the geotextile tubes

 

Portion of the polymer system used to treat the dredged sediment prior to dewatering

 

 

 

(Photo 5 of 8) Water released from the geotextile tubes during the dewatering process (filtrate) was collected and treated in an on site wastewater treatment plant.  Suspended solids were removed from the filtrate in these inclined plate separators or lamella clarifiers.

  Lamella clarifiers used to treat water released from the geotextile tubes
     

(Photo 6 of 8)  Flow from the lamella clarifiers was then filtered through these pressurized horizontal sand filters.

  Sand filters
     

(Photo 7 of 8)  Filtered water from the sand filters was then treated with granular activated carbon (GAC) to remove any remaining organic contaminants.

  Granular Activated Carbon (GAC) adsorption units
     

(Photo 8 of 8) When dredging was complete, the sediment containment facility was prepared for capping and closure.

  Prepping the sediment containment facility for capping and closure
   

Next project: Creosote Contaminated Pond Remediation

Return to Featured Sediment Dewatering Projects page