|
Media
|
|
Summary
Infrastructure Alternatives, Inc. (IAI) was the General Contractor for all landside operations on the Ottawa River Remediation project, which was conducted over the course of the 2010 construction and dredging season. The project involved hydraulic dredging of 242,000 cubic yards of contaminated sediment from the Ottawa River to geotextile tubes for dewatering and wastewater treatment. The dredged sediment was pumped by the dredging contractor from the Ottawa River to the Hoffman Road Landfill in Toledo, Ohio, where two separate dewatering pads had been constructed for the purpose of dewatering the dredged sediment. Sediment contaminants included polychlorinated biphenyls (PCBs), polyaromatic hydrocarbons (PAHs) and heavy metals.
About 16,000 cubic yards of the most contaminated dredged material was regulated by the Toxic Substances Control Act (TSCA), and was pumped to the TSCA dewatering pad for chemical conditioning and dewatering in geotextile tubes. The remaining dredged sediment was not regulated by TSCA and was pumped to a second, non-TSCA dewatering pad where the dredge slurry was injected with polymer, screened to remove debris and coarse grain material, thickened in gravity thickeners and finally, dewatered in geotextile tubes. About 226,000 cubic yards of non-TSCA sediments were dewatered in 41,000 lineal feet of 75 – 85 foot circumference geotextile tubes, stacked six layers high over the terraced non-TSCA dewatering pad.
Storm water from the dewatering pads, clear water from the gravity thickeners and geotextile tube weep water was collected and treated in a temporary on-site wastewater treatment plant (WWTP). The WWTP design and construction was fast-tracked to accommodate a 1 year dredging schedule. The WWTP, with 4,000 gpm maximum capacity, was installed in just 32 days.
Treated water was then discharged back to the Ottawa River under an NPDES permit. Several water treatment processes were incorporated into the on-site WWTP, including: lamella inclined plate clarifiers, multi-media filters and bag filters to remove suspended solids; and Granular Activated Carbon (GAC) adsorption vessels to remove dissolved organic contaminants. The WWTP had a design capacity of 4,000 gallons per minute and treated over 500 million gallons of water during the performance of the Ottawa River Remediation project. No NPDES effluent quality permit violations occurred.
Dewatered TSCA sediment was removed from the geotextile tubes after sufficient dewatering and transported with trucks to a nearby hazardous material landfill. Dewatered non-TSCA sediment was capped in place and will remain in the Hoffman Road Landfill permanently.
|
|
Services provided
-
Sediment dewatering pads design
-
Geotextile tube header design, installation
-
Polymer dilution & polymer feed systems installation, operation
-
Gravity thickener installation, operation
-
Geotextile tube dewatering of 242,000 cubic yards contaminated sediment
-
4,000 gpm wastewater treatment plant design, construction
-
Wastewater treatment plant start-up, operation & maintenance
-
General conditions for landside activities
-
OSHA 40 hour HAZWOPER certified staff
-
Site Specific Health & Safety Plan
-
Air monitoring & personnel monitoring
-
Equipment decontamination & demobilization
|
|